dwma/dpap
 
QUICK SEARCH :

Profile


DPAP (Drought Prone Area Programme) has been created as a separate establishment on Dt 28-09-2001vide G.O.Ms.No 275 PR&RD(RD-II) Dept. Dt 05-09-2001by bifurcating from DRDA exclusively to look after development of human resources and Natural Resources on Watershed Basis. Consequently, the Govt. vide GO.MS.No.84 PR&RD (RD-IV) Dept. Dt.22-03-03 have issued orders changing the nomenclature of Project Director DPAP as Project Director District Water Management Agency (DWMA) uniformly for all districts in the state
The Chairman of the Project is District Collector and the Project is looked after by Project Director who is assisted by M.D.T (Multi Disciplinary Team) having one Deputy Executive Engineer, Assistant Conservator of Forest, Assistant Director of Agriculture, Assistant Engineer and Agriculture Officer as members. There are 157 Watersheds in different Schemes being monitored with the help of 17 P.I.As (Project implementing Agency)14 of them being N.G.Os. The Project is also monitoring Neeru – Meeru, Food for Work Programme, AP WALTA and APMIP in the District
 
Schemes
 
DPAP

The DPAP watersheds have been started during the year 1995-96 in Drought effected Mandals and subsequently sanctioning every year. The details are furnished here under;
 
DPAP Batch Number No. of Watersheds No. Blocks covered No. of Mandals covered Sanction year
I 10 2 6 1995-1996
II 06 2 3 1996-1997
III 14 2 4 1997-1998
IV 15 2 5 1998-1999
V 16 2 7 1999-2000
VI 14 2 5 2000-2001
VIII 12 2 5 2002-2003
HARIYALI-I 08 2 4 2003-2004
HARIYALI-II 08 2 4 2004-2005
 
Mandals Covered under DPAP

1. VR Puram 2. Chintoor 3. Kothagudem 4. Palawancha 5. Enkooru 6. Julurupadu
7. Chandrugonda.

The ultimate aim of watershed management is to achieve and maintain a balance between resources development to increase the welfare of the population and resource conservation to safeguard resources for future exploitation and to maintain ecological diversity both for ethical reasons and as an assumed pre-requisite the survival of mankind.
 
 
Andhra Pradesh Micro Irrigation Project (APMIP)

The APMIP has been launched in the District in November 2003 and the achievements are as follows:
 
Target for Vision 2020 --  
Target under APMIP -- 10,300 Ha.
Target for First Phase -- 7763 Ha.
 
Financial Assitance
 
Total Project -- 52.5 Crores
NABARD Assistance -- 26.25 Crores
Credit by Bankers -- 26.25 Crores
No of Mandals to be covered -- 46.
 
1st phase Target for Khammam District
 
Project Cost -- 34 Crores
Government Subsidy -- 17 Crores
No of Farmers Applied -- 6130
Target for 1st phase -- 7763 Ha.
Achievement in 1st Phase (Khammam) -- 2404.89 Ha.
Financial Achievement -- 1.30 Crores
Number of Farmers Covered -- 1224

Drip (No of Farmers)

-- 186
Area covered under Drip -- 341.2
Spinklers (No of Farmers) -- 1038
Area covered under Spinklers -- 2062.99
Total amount released from Govt -- 250 Lakhs
Amount claimed upto 2004 -- 117 Lakhs
 